Digital Project Performance Monitoring Using Microsoft Project: A Case Study of a Small-Scale Construction Project
Keywords:
Earned Value Method, Microsoft Project, Work Breakdown Structure, Project Management, Cost-effectiveAbstract
This study analyzes the scheduling optimization of a single-story shophouse construction project using Microsoft Project based on Earned Value Method (EVM) with the Work Breakdown Structure. The research adopts a quantitative approach by measuring cost and schedule performance indicators across three monitoring periods during the project execution. The EVM approach connects three dimensions scope, schedule, and budget through the Cost Variance (CV) and Schedule Variance (SV) indicators. CV reflects the difference between the planned budget value for completed work packages and the actual costs incurred; a positive value indicates work packages completed at lower cost than planned, while a negative value indicates expenditure exceeding the planned budget. SV reflects whether work packages are completed ahead of or behind schedule. The project covers 11 main work groups organized hierarchically in Microsoft Project's WBS, with a planned duration from October 1, 2025 to December 29, 2025, at a total budget of Rp253,975,641. Results show that as of the monitoring status date, the project achieved 79% task completion with Rp217,743,382 in actual expenditure. EVM analysis reveals that five work groups Pekerjaan Persiapan, Pondasi, Cor Beton, Pintu Kusen, and Atap were completed on time and within budget (SV = 0, CV = 0), while Pekerjaan Listrik showed the most critical deviation with a schedule variance of −2 and a negative cost variance due to only 29% completion. WBS-based scheduling through Microsoft Project is proven effective in improving project transparency, facilitating resource management, and enabling early detection of cost and schedule deviations.
References
Anastasiu, L., Câmpian, C., & Roman, N. (2023). Boosting Construction Project Timeline: The Case of Critical Chain Project Management (CCPM). Buildings, 13(5), 1249. https://doi.org/10.3390/buildings13051249
Aprillia, S. C., Wasono, W., & A’yun, Q. Q. (2023). Optimalisasi biaya dan waktu pelaksanaan pembangunan rumah tinggal di Kecamatan Rantau Pulung Kutai Timur menggunakan Critical Path Method (CPM) dan Program Evaluation and Review Technique (PERT). Basis : Jurnal Ilmiah Matematika, 2(1), 11–24. https://doi.org/10.30872/basis.v2i1.1000
Ayu Herzanita. (2019). Penggunaan Standard WBS (Work Breakdown Structure) pada Proyek Bangunan Gedung. Jurnal Infrastruktur, 5(1). https://doi.org/10.35814/infrastruktur.v5i1.613
Cerezo-Narváez, A., Pastor-Fernández, A., Otero-Mateo, M., & Ballesteros-Pérez, P. (2020). Integration of cost and work breakdown structures in the management of construction projects. Applied Sciences (Switzerland), 10(4). https://doi.org/10.3390/app10041386
Chauhan, N. (2025). The Role of Earned Value Management In Driving Cost and Schedule Performance in Engineering Projects. International Journal of Research -Granthaalayah, 13(5). https://doi.org/10.29121/granthaalayah.v13.i5.2025.6214
Elserougy, M., Khodeir, L. M., & Fathy, F. (2024). Practices and techniques for construction projects cost control- a critical review. HBRC Journal, 20(1). https://doi.org/10.1080/16874048.2024.2337060
Gertzen, W. M., van der Lingen, E., & Steyn, H. (2022). Goals and benefits of digital transformation projects: Insights into project selection criteria. South African Journal of Economic and Management Sciences, 25(1). https://doi.org/10.4102/sajems.v25i1.4158
Khahro, S. H., Shaikh, H. H., Zainun, N. Y., Sultan, B., & Khahro, Q. H. (2023). Delay in Decision-Making Affecting Construction Projects: A Sustainable Decision-Making Model for Mega Projects. Sustainability (Switzerland), 15(7). https://doi.org/10.3390/su15075872
Mayo-Alvarez, L., Alvarez-Risco, A., Del-Aguila-Arcentales, S., Sekar, M. C., & Yáñez, J. A. (2022). A Systematic Review of Earned Value Management Methods for Monitoring and Control of Project Schedule Performance: An AHP Approach. Sustainability (Switzerland), 14(22). https://doi.org/10.3390/su142215259
Metwally, Y. B., Elsaid, A. M., Elhamaida, S. M., & Abd Elsamad, M. A. E. (2025). Project Navigating: A Guide to Successful Construction Project Management. Advanced Sciences and Technology Journal, 2(1). https://doi.org/10.21608/astj.2025.345552.1030
Moradi, S., Kähkönen, K., & Aaltonen, K. (2020). Project managers’ competencies in collaborative construction projects. Buildings, 10(3). https://doi.org/10.3390/buildings10030050
Ningsih, A., Surahman, S., Ariani Aisyiah, S., Syahara, A., & Bayhaqi, A. (2025). Implementation of Critical Path Method (CPM) in Project Management of Type 45 House Construction in Samarinda. Journal of Business Management and Economic Development, 3(02), 758–770. https://doi.org/10.59653/jbmed.v3i02.1657
Odedairo, B. O. (2024). Assessing the Influence of Various Work Breakdown Structures on Project Completion Time. Engineering, Technology and Applied Science Research, 14(2). https://doi.org/10.48084/etasr.7023
Okoro, C., Olaleye, A., & Owojori, O. (2024). The risks of private sector investment in affordable housing development: An Afrocentric perspective. Journal of Infrastructure, Policy and Development, 8(1). https://doi.org/10.24294/jipd.v8i1.2691
Panquet, Q., Bourgault, M., Pellerin, R., Danjou, C., & Perrier, N. (2024). A Process-Improvement Method for Implementing Earned Value–Based Project Management in Organizations. Journal of Construction Engineering and Management, 150(12). https://doi.org/10.1061/jcemd4.coeng-15041
Priyo, M. (2021). Earned Value Management System in Indonesian Construction Projects. International Journal of Integrated Engineering, 13(3). https://doi.org/10.30880/ijie.2021.13.03.005
Proaño-Narváez, M., Flores-Vázquez, C., Vásquez Quiroz, P., & Avila-Calle, M. (2022). Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections. Buildings, 12(3). https://doi.org/10.3390/buildings12030301
Sigit, R. A. P., Al-Muqaffa, F. W., & Sutrisno, S. (2024). Evaluasi Penjadwalan Waktu Pada Proyek Pembangunan Rumah dengan Metode CPM (Studi Kasus: Pembangunan Rumah Tinggal di Perumnas Kabupaten Karawang). Go-Integratif : Jurnal Teknik Sistem Dan Industri, 4(02), 148–157. https://doi.org/10.35261/gijtsi.v4i02.10876
Sima, K. (2022). Executing, Monitoring and Controlling a Project, the Right Way. Researchgate, (December).
Soeparyanto, T. S., Nuhun, R. S., Ismayana, I., Apriani, M., & Hado, H. (2024). Penggunaan Standar Metode Work Breakdown Structure (WBS) Pada Proyek Pembangunan Gudang BPBD dan Rumah Jabatan Dandim. Sultra Civil Engineering Journal, 5(2). https://doi.org/10.54297/sciej.v5i2.626
Surahman, S., Kusumah, A., Tiara, T., Tomby, R. S., & Nurmaulida, N. (2024). Project management planning of the small house construction in samarinda using the critical path method (CPM). Enrichment : Journal of Management, 14(3), 476–487. https://doi.org/10.35335/enrichment.v14i3.1939
Varajão, J., Lopes, L., & Tenera, A. (2025). Framework of standards, guides and methodologies for project, program, portfolio, and PMO management. In Computer Standards and Interfaces (Vol. 92). https://doi.org/10.1016/j.csi.2024.103888
Wang, T., & Chen, H. M. (2023). Integration of building information modeling and project management in construction project life cycle. In Automation in Construction (Vol. 150). https://doi.org/10.1016/j.autcon.2023.104832
Widyarso, R., Witjaksana, B., & Purnama, J. (2025). Analysis Of Time And Cost Performance In Construction Projects Using The Earned Value Management Method. Asian Journal of Engineering, Social and Health, 4(4). https://doi.org/10.46799/ajesh.v4i4.590
Zaneldin, E., & Ahmed, W. (2024). A Generic Framework for Managing Schedule and Cost Risks of Construction Activities Using PERT and the EV Technique. Buildings, 14(7). https://doi.org/10.3390/buildings14071918
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Lintang Putra Anthama, Athallah Rafi Febrian, Fadil Fathan, Mohamad Digi Atmaja, Rika Ismayanti

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.